Determine the Most Important Construction Risks and Know the Degree of Their Impact on Construction Projects in Iraq

Determine the Most Important Construction Risks and Know the Degree of Their Impact on Construction Projects in Iraq

Haneen Z. Faeq Tareq A. Khaleel*

Department of Civil Engineering, College of Engineering, Technology University, Baghdad 10001, Iraq

Department of Civil Engineering, University of Technology-Iraq, Alsinaa Street 52, Baghdad 10001, Iraq

Corresponding Author Email: 
Tareq.A.Khaleel@uotechnology.edu.iq
Page: 
933-943
|
DOI: 
https://doi.org/10.18280/ijsse.130517
Received: 
29 June 2023
|
Revised: 
9 October 2023
|
Accepted: 
14 October 2023
|
Available online: 
10 November 2023
| Citation

© 2023 IIETA. This article is published by IIETA and is licensed under the CC BY 4.0 license (http://creativecommons.org/licenses/by/4.0/).

OPEN ACCESS

Abstract: 

By performing the Statistical Package for Social Sciences (SPSS) V26 and statistical analysis, this study aims to identify, evaluate and examine risk variables that may impact construction projects in Iraq. The reliability and internal consistency of the factors were tested using Cronbach's alpha coefficient, where Cronbach's alpha for this research was in the range of 0.923, which provides a strong indicator of the validity and reliability of the questionnaire. The relative importance index will be used to measure the degree of these risks. Field, personal and survey interviews were used to obtain these data. The survey consists of two components, the first of which is a sample of general information, and the second part discusses the possibility of risks occurring, having an impact, and the identification of 44 factors. The census results showed, by analyzing the responses from 44 workers, that only 15 factors significantly impacted the occurrence of risks in construction projects in Iraq. These factors affected the project objectives in terms of cost, time and quality, which led to the project not being completed on time. In addition to increase the cost of construction due to failure to take risks into account.

Keywords: 

risk management, risk assessment, risk factors, degree of risk

1. Introduction

Risk is an important decision-making factor for construction projects and can influence how successfully a project will be implemented. If not handled appropriately, it can lead to cost overruns, schedule delays, and even poor quality [1].

Any program has a certain level of Risk. The risks are increasing due to construction projects' increasing complexity and scale. In addition, there are local economic, political, social and cultural elements that will have an impact on the project. A project risk is a risk that, if it does happen, could impact at least one project objective in a good or bad way. Risks can arise through exposure to the effects of uncertainty. Possible outcomes include an event occurring in the context of the project and affecting the objectives. Considerations include the possibility of profit or loss or deviating from a planned or desired outcome due to the uncertainty involved in selecting a particular action plan [2]. Others define Risk as being initiated by the project without concern for potential harm or loss [3].

Threat describes this type of Risk. The threat is defined as an unfavorable state or condition of the project, a set of negative circumstances, the chance that it will negatively affect the project goal if it occurs, or the possibility of unfavorable changes [4].

It is difficult to eliminate risks from a construction project. Therefore, a formal risk management strategy is required to deal with many risks. Risk management is a legal and systematic process to identify, analyze and respond to risks throughout the project's life to achieve the highest level of risk elimination, mitigation and control [5]. Companies need to structure and establish effective risk management processes [6]. Project risks must be identified, assessed, analyzed and responded to for the main actions to show systematic risk management [7]. The risk management system, an essential component of engineering project management, is associated with issuing the best judgments and developing policies to ensure the least possible risks [6].

Risk assessment uses qualitative approaches to prioritize risks affected by project objectives based on determining their likelihood of occurrence and severity. Their influence and quantitative approaches to describe Risk include decision tree analysis, sensitivity analysis, and Monte Carlo simulations [8].

For the reasons of this research, the following reasons were taken into account:

1. The lack of an effective risk management system in Iraqi construction projects leads to many risks that impact the project's initial objectives.

2. To reduce the possibility of exposure to risks and their impact on the cost of construction projects in Iraq.

3. Insufficient documentation records the risks encountered during the project life cycle.

Therefore, the main risk variables affecting Iraqi construction projects and their severity and impact must be identified, evaluated and understood in this study. All projects are fraught with risks, and most of these construction projects suffer from not considering these risks when calculating the project's cost estimates.

This paper is organized as follows: preliminaries.

Described in Section 2. Construction Project Risk Rating in Section 3. Process risk management in the construction project in Section 4. Methodology in Section 5, Sources of Data in Section 6, The questionnaire's design in Section 7, Collection of data in Section 8, Analysis of data in Section 9, Data analysis and discussion in Section 10 and finally a conclusion in Section 11.

2. Preliminaries

This section will present the definition of Risk, the difference between certainty and uncertainty in Risk, and the reasons for taking risks as threats.

2.1 Risk definition

Risk is the exposure to an unknown's effects. Everything conceivable may happen in the framework of a project that will change the aims. It considers the possibility of gain or loss, as well as departure, due to the uncertainty involved in choosing a specific path of action from a desired or anticipated end. Hence, Risk has two elements: the likelihood of something occurring and the ramifications for the project goals like time, money, and quality [2].

Some people define threats as a source of danger, the potential for disaster or loss, or an activity undertaken without regard to the possibility of injury or loss. Threats can include any unfavorable event, a startling situation, a risk that, if realized, would be detrimental to the project's goal, or the potential for unfavorable developments [9].

2.2 Certainty and uncertainty in risks

Decisions can be made in both assured and uncertain situations. There are debates over whether Risk and uncertainty are the same concept. Some studies distinguish given the relationship between Risk and uncertainty may be described in terms of impacts and probabilities, but uncertainty is more challenging to express. To quantify scientifically, particularly based on likelihood [4].

The definition of certainty is the situation in which all factors impacting Risk can be assessed, and decision-making procedures result in a specific, predictable result [10].

However, this occurs seldom and just in locked systems. An uncertain situation is one in which it is unclear which of several potential outcomes has already happened or will happen. Although all dangers are unexpected, not all uncertainty is harmful [11].

Certainty occurs only when it is possible to predict exactly what will occur over the period the decision applies to. In the building industry, this is rare. Several writers do not distinguish education and learning in Wales between Risk and uncertainty (2001) used the following definitions of Risk and uncertainty [12]:

1. There is Risk when a decision is justified in terms of a range of possible outcomes. Known probabilities may be attributed to the outcomes.

2. There is uncertainty when there are several possible outcomes to a sequence of action, but the likelihood of each possibility is unknown.

2.3 The Reasons to take risks as threats

The sources of dangers in construction project activity are not fully explained in any thorough study. Some writers attempted to recognize the danger-causing elements in building projects in their investigations and attributed Roilamela and Lobello's high threats to [13]:

1. A significantly fragmented industry.

2. The industry is extremely subject to the financial cycle.

3. serious competition is a result of an oversupplied market.

4. Organizational problems.

5. Accounting, in which errors in financial data generated for management occur.

6. Expanding the scope of the project.

7. Unacquaintance with a new geographical location.

8. Transitioning to a new style of building.

9. A change in key people.

A review of previous studies over the past three decades on risk identification and assessment Factors in construction projects considered nearly 1,000 global projects from different countries. It can be concluded from previous studies that there is a lack of knowledge about risk management in construction projects. However, the most important risk factors affecting the cost of construction projects are insufficient financial allocation, planning, scheduling, financing, payment, poor communication between construction parties, and emergency changes during the construction phase. Various service construction projects were taken to determine how these factors affect the cost. Projects that caused an increase in the final construction cost of those projects.

3. Construction Project Risk Rating

The hazards connected to the construction sector can be roughly categorized as follows [14]:

1. Organizational risks: Organizational risks consist of contractual relationships such as the relationship between the contractor and the second contractor and the misunderstanding and agreement that occurs between them, the experience of the contractors, the attitudes of the participants, the inexperienced workforce such as providing staff with little experience to benefit from some of the worker's wages, and communications such as poor communication between The contractor and the employer promise to follow up on matters first.

Figure 1. Classification of construction project risks

2. Risks associated with site building: Include worker productivity, the state of the job site, equipment breakdowns, design modifications, higher quality requirements, and new technologies.

3. Technical hazards: These include risks related to incomplete designs, inadequate specifications, poor on-site investigations, changes in the scope and methods of construction, a lack of resources, and other factors.

4. Political or security concerns: Include alterations to laws and regulations, safety and pollution rules, law and order, war, and civil unrest.

5. Financial risks: Include higher material costs, decreased demand for the product on the market, fluctuating currency rates, late payments, incorrect appreciation taxes, etc.

6. Legal risks: Delay in receiving operational advances and confiscation of project lands by the state.

7. Environmental risks: Natural disasters, weather, floods and environmental pollution, as shown in Figure 1.

4. Process Risk Management in the Construction Project

The nature of the construction industry makes risk management (R.M.) essential, a crucial strategy typically used in projects with high uncertainty. More structured planning, monitoring, and control processes help identify these risky investments. Analyzing past failures and concluding is the fastest way to identify risks [15].

The most frequent and typical types of projects are construction projects, which have a variety of characteristics, such as a specific objective, time limit, financial restrictions and economic requirements, unique regulatory and legal requirements, complexity, and methodological qualities. As a result, each investment project is a complex system in and of itself.

Projects involving construction, in particular, face various risk factors and complex relationships that will have an impact. Direct, indirect, overt, covert or unexpected relationships are difficult [16].

Determining the risk factor is the initial stage of the iterative risk management process (RMP), which also involves qualitative and quantitative evaluations of the effects of risks on the project. Create risk management strategies to keep the project participants' maximum Risk and return structure [17, 18].

Throughout a project's life cycle, risk management is a systematic and formal procedure that must be implemented in a construction project. It is divided into three steps. These phases involve completing risk management planning, identifying, Risk analysis, and planning for risk response and control. Project risk management aims to increase the possibility and effect of favorable occurrences and decrease the likelihood and impact of unfavorable events. Several authors describe RMP as identifying, analyzing, and planning risks. As a result, the current research proposal of a risk management technique included these steps of the RMP. However, the Project Management Institute (PMI) has discussed the refrigerant management plan.

According to the PMI Project Management Knowledge Book, risk management is a methodical procedure for detecting, assessing, and addressing project risks (2013). Project objectives entail maximizing the chance and effects of favorable occurrences and limiting the probability and effects of unfavorable events. Here, each risk management component is covered from the standpoint of a building project.

It identifies risks based on personal interviews conducted with several experienced engineers in the field of construction and contractors, previous studies, and a questionnaire survey. Risk analysis is based on quantitative and qualitative analysis methods, where quantitative analysis is performed using different methods, including probability analysis, Monte Carlo simulation technique, sensitivity analysis, break-even point analysis, and others. Qualitative analysis is carried out using several analysis methods that can be used to evaluate and enhance the effectiveness of risk management in building projects, including direct judgment, comparison options, ranking of options, descriptive calculation, risk probability, impact probability analysis and impact matrix, risk classification, and quality assessment. Risk statements and risk assessment. After identifying and analyzing the project risks, it is necessary to develop an appropriate risk response strategy to implement the required countermeasures against the adverse effects of the risks on the project objectives. Making decisions to increase opportunities and reduce threats to project objectives is developing a risk response plan such as risk avoidance, acceptance, transfer, and retention. Risk monitoring and control is a system for monitoring residual risks, tracking known risks, finding additional risks, and evaluating risk management procedures in all project parts, as shown in Figure 2.

Figure 2. Framework for risk management [2]

5. Methodology

The research approach followed can be summarized as follows: There are 44 risk factors. Based on individual interviews, literature reviews, and field surveys, they were discovered and grouped into seven sources of Risk. As shown in Figure 1. The questionnaire was then distributed to the Ministry of Construction and Housing, the public sector, and a contracting company. Companies in the private sector. Ninety-two questionnaires were distributed to specialized engineers and engineers of different ages of experience, as shown in Table 3.

Seventy questionnaires were received and approved for statistical analysis. Incomplete responses to any questionnaire items led to nine forms being rejected, and 13 other forms were not returned, bringing the response rate to 76% of the total sample size. As a result, the questionnaire was analyzed using a reliability test, where Cronbach's alpha coefficient (C) is used to measure internal consistency. The Cronbach's alpha coefficient (C) measures internal consistency. To give the measurement to evaluate the validity and the inner scale or thickness of the test and the relative importance index approach to examine the acquired data to determine the value of the identified factors. It depends on the probability of the Risk occurring and the consequences (consequences). Then, the risk score was found, and a risk assessment was performed based on the classification of risk factors, the severity of the risks, and the extent of the impact of the RII periods, which will be explained in the next stages. Therefore, the results identified the most important risk variables that affect construction projects at the planning stage in Iraq.

6. Sources of Data

Many methodological approaches have been used to detect and assess the risks that have an impact on building project costs, and they include the following:

1. Literature reviews.

2. Interviews.

3. Survey questionnaire.

6.1 Literature reviews

Extensive literature reviews of prior studies closely related to risks in construction projects and their management, identification, and evaluation gave the researcher information and ideas on the topic. The study's accuracy was significantly improved by attempting to cover as much as possible of the risks affecting the cost of projects from prior research studies. Yet a number of elements were first determined by referencing earlier study investigations.

6.2 Interviews

Personal interviews with those in charge of construction, including consultants, seasoned civil engineers, contractors, supervisors, and even workers, made it easier to identify the most significant risks that affect the cost by offering suggestions, advice, and other details that would improve the study's accuracy. Table 1 shows the unique qualifications for engineer interviews.

Table 1. Unique qualification for engineering interviews

NO.

Job Title

Years of Experience

The Workplace

1

Projects Manager

31

Al Rasheed General State Constructional

2

Senior Chief Engineer

30

AL-Mansour State Company

3

Academic

38

University of Baghdad

4

Senior Chief Engineer

30

AL-Mansour State Company

5

Consultant

37

Engineering Consulting Center

6.3 Survey questionnaire

As described, a questionnaire is a research instrument used to gather data from respondents based on their thoughts and work experience. So, the questionnaire form should have several inquiries and other stimuli to be the topic of subsequent statistical research.

7. The Questionnaire's Design

According to the survey's questionnaire, several specific danger variables may influence Iraqi building projects.

Field observations, in-person interviews with several engineers and managers working in the housing and construction industries, information gathered from the literature review, and Two sections make up the questionnaire form, the first of which requests general information. About the research project, A second part of the questionnaire included identifying 44 Risk factors. Respondents were asked to indicate the likelihood of occurrence and the effect level regarding their impact on construction projects in Iraq during the planning stage. Each factor on a five-point Likert scale is Strongly Accept, Accept, Neutral, Disagree, or Strongly Disagree. Housing and Construction Sector engineers formed the study community based on the research's aim. Before the questionnaire was made public, a commission of five arbitrators was constituted to evaluate its performance, as shown in Table 2. This committee studied these various risk factors, and some factors were added and deleted until the final form of the questionnaire was reached, as shown in the attached appendix.

Table 2. Personal qualification of arbitrators

NO.

Job Title

Experience Years

Work Place

1

Projects Manager

31

Al Rasheed General State Constructional

2

Senior Chief Engineer

35

AL-Mansour State Company

3

Lecturer/Ph.D

32

University of Central Technical

4

Lecturer/Ph.D

25

University of Technology

5

Lecturer/M.SC

18

University of Baghdad

8. Collection of Data

The study's results were obtained by distributing surveys across the housing construction sectors, with a sample size of at least 30 respondents. The questionnaire is distributed to more than 30 people because it will give more accurate results and include all opinions. Some incomplete questionnaire forms contain errors and are ignored [19].

Table 3. The questionnaire was distributed

% of Response

Received

Distributed

Workplace

NO.

100%

20

20

Ministry of Business and Housing

1

100%

7

7

Al-Mansour Contracting Company

2

83%

29

35

National Center for Engineering Consultation

3

47%

14

30

Accurate Surveying Contracting Company

4

76%

70

92

Total

In total, 92 surveys were distributed to various engineers with varying degrees of expertise in the building business. The answers included in the final analysis numbered 70 were included in the analysis. Moreover, some forms were received incomplete. Table 3 shows how questionnaires were distributed, including how many were given out and to whom; for each directorate and project included in the research sample, 76% of those surveyed answered.

9. Analysis of Data

IBM SPSS V26 and Microsoft Excel applications were used for the analysis.

9.1 Reliability testing

Reliability research There are two methods used to carry it out. External reliability analysis comes first. Testing is done repeatedly, and results are compared. The second technique is internal reliability analysis. Uses As soon as the information is gathered for dependability analysis. This technique the analytical process includes several components. Credibility The consistency of the objects is tested to determine the modulus.

Internal reliability analysis often uses techniques like Half Spearman-Brown and Alpha Cronbach [20].

The reliability and internal consistency were evaluated for each questionnaire component using Cronbach's alpha coefficient (C). (C) always has a value between 0 and 1. The stability improves as the value approaches one, and vice versa. Cronbach's alpha values for this search are in the range of 0.923, according to Table 4, which indicates the validity and reliability of the questionnaire, which should be more than 0.7 [21].

Table 4. A questionnaire's Cronbach's alpha

Cronbach's Alpha

No. of Item

Category

No.

0.846

8

Organizational

1

0.731

6

Worksite

2

0.844

7

Technical (related to the contractor)

3

0.650

4

Technical (related to the employer)

4

0.350

5

political or security

5

0.787

6

Financial

6

0.705

4

Legal

7

0.588

4

Environmental or natural

8

0.923

44

Total (all items of the questionnaire)

9.2 Normality test

A normality test should be completed to determine if the data collected from a questionnaire is normally distributed. The Shapiro-Wilk test, Kolmogorov-Smirnov test, skewness, kurtosis, histogram, box plot, P-P plot, and Q-Q plot are just a few of the methods that may be used to check for normalcy. And the Kolmogorov-Smirnov and Shapiro-Wilk tests are the most often used techniques. The Kolmogorov-Smirnov test was chosen because the sample size was more than 50.

Table 5 shows the results of the standardization of the questionnaire data.

The results showed that the significant level of the included data is greater than (mark 0.05). Therefore, all survey data are distributed in a normal distribution. In addition to performing a normality test, skewness and kurtosis values are calculated. Skewness is a measure of the irregularity or homogeneity of a normal distribution. Standard deviation is widely regarded as one of the most important and accurate measures of dispersion and the most common and commonly used in statistical analysis. While kurtosis is a measure of a distribution's peak, the data's distribution is symmetric when it progresses in the same direction to the left and right of the central point.

Table 5. Normal distribution test

Category

Kolmogorov-Smirnov

Statistic

Sig.

Probability of Risk occurrence

.200

.097

Impact of Risk

.200

.099

Uses some descriptive statistics to demonstrate shown in Table 6.

Table 6. Sample descriptive statistics

No.

Statistic Function

Probability

Impact

1

Mean

.703

.526

2

Median

.711

.532

3

Variance

.002

.003

4

Std. Deviation

.043

.056

5

Range

.244

.298

6

Skewness

-.237

.071

7

Kurtosis

1.257

.696

9.3 The index of relative importance

Check out survey responses on statistical measurements for extra inspiration. By evaluating the Relative Importance Index, these parameters were rated according to the significance of their influence on building projects (RII). It is used to determine how crucial it is to prioritize the many risks that impact building projects during the planning stage. The significance index was the percentage calculated for each risk factor by using the Eq. (1) [22]:

$R I I=\Sigma W / A * N(0 \leq R I I \leq 1)$         (1)

W: is the score assigned to each component and typically varies from (1 to 5).

(Where "1" is "no" and "5" is "always");

N: is the size of a file sample questionnaire, and A: is the maximum score (in this case, 5).

(i.e., 70 in this study).

Whereas the relative relevance index was used in the second section of the questionnaire to evaluate all risks.

9.4 Degree of risk

Using the relative relevance index (RII) for each Risk's chance of occurrence and its effect on the elements listed in the questionnaire it is used to conduct a qualitative risk analysis of the risk factors that result in cost overruns for building projects. The equation can calculate the degree of Risk (2) [23].

Degree of Risk $=$ Likelihood ${ }^*$ Effect           (2)

Determine the deviation (D) between the highest risk score value and the RII intervals to assess the risk score's effect level. and the lowest value, as seen in Table 7 [24].

D=0.559-0.221=0.338.

Table 7. Level of RII interval influence

Influence Level

RII Intervals

Minimum Limit

Maximum Limit

Extremely Low

0.221-0.255

0.221

0.221+10%*D

=0.255

Low

0.256-0.332

0.256

0.256+22.5%*D

=0.332

Medium

0.333-0.409

0.333

0.333+22.5%*D

=0.409

High

0.41-0.486

0.41

0.41+22.5%*D

=0.486

Extremely High

0.487-0.563

0.487

0.487+22.5%*D

=0.563

Table 7 shows the influence level of the RII intervals used to determine the risk severity/score based on the minimum and maximum risk severity limitations.

10. Data Analysis and Discussion

10.1 Survey results

The statistical analysis is divided into two primary sections to make the questionnaire findings more understandable.

10.1.1 General information in part one

The sample demographic information from the survey respondents is described in a respondent profile. Demographic information is primarily used to evaluate respondents' capacities and understanding of the hazards that impact building project costs. Figure 3 displays the proportion of answers from each workplace. The consulting centre (41%) constituted the largest proportion, as for the Ministry of Construction and Housing (29%), the Survey Accuracy company (20%), and the Al-Mansour Contracting Company, respectively.

Figure 4 indicates the ratio of respondents working in the general public to those in the business sector; 87% are in the former, while 13% are in the latter.

Figure 5 displays the proportion of engineers in each engineering speciality who answered survey questions. It was determined that graduates from general civil engineering made up the largest percentage of the data sample (64%), while graduates from other engineering disciplines made up the remaining percentage. Such as structural engineering, project management engineering, and building and construction engineering are represented, respectively, by (14%), (13%), and (9%) from the sample data.

Figure 6 shows that the biggest percentage (63%) of the engineers who answered the questionnaire held a Bachelor of Science. 33% of engineers have a master's degree. Degree (3%) of engineers hold a Ph.D. At the same time, the percentage was (1%) for engineers having a diploma.

Figure 3. Workplace response

Figure 4. Work sector

Figure 5. Engineering specialization

The number of years of experience the engineers who responded to the survey have been shown in Figure 7. Most of the study sample, or 34%, consisted of engineers with more than ten years of experience. The number of engineers with experience between 5 and 10 years was 32%. Engineers with experience of between 10 and 15 years came in second with a percentage of 27%, and engineers with experience of more than five years came in last with a percentage of (7%).

It is clear from the Table that (54%) are females, and this percentage represents more than half, while the rest (46%) are males, as shown in Figure 8 below.

Figure 6. Academic degree

Figure 7. Years of experience

Figure 8. Distribution according to gender

10.1.2 The likelihood of risks happening and the severity of those risks make up the second section

Table 8 shows the assessment given the severity and classification of the selected danger variables that are detected essential risk factors for carrying out work that does not comply with rejection results from not meeting requirements for return of work, schedule inaccuracy, delay in payment of advances, failure to finance the project. According to the questionnaire, the last eleven factors have little effect on Iraqi building projects during the planning stage. The table below shows qualitative evaluation and rating of the risk factor.

10.2 The most important risk factor

Following a qualitative study and ranking of the risk score, 15 of the 44 risk variables are considered the most important risk factors within the risk category as shown in Table 9 and Figure 9.

Table 8. Qualitative assessment and ranking of the risk factors

No.

Risk Factor

Probability of Occurrence

Degree of Impact

Risk Score

Influence Level

Rank

1

Assigning work to an incompetent contractor

0.817

0.684

0.559

Very High

1

2

The deterioration of the security situation

0.769

0.621

0.478

High

2

3

The presence of obstacles at the site (such as groundwater, water pipes, electrical installations... etc.)

0.754

0.593

0.447

High

3

4

Occupation of the project by another party leads to a delay in the contractor's receipt of the project

0.751

0.593

0.445

High

4

5

Unavailability of designs for service networks that cross the location (such as electricity, telephone, water, etc.)

0.751

0.589

0.442

High

5

6

Insufficient financial allocations to complete the works

0.749

0.584

0.437

High

6

7

Late arrival of some materials and equipment from the country of origin

0.749

0.581

0.435

High

7

8

Mismatch of plans (structural, architectural) or contract documents

0.743

0.576

0.428

High

8

9

Variations between implementation and needed specifications as a result of plan and specification misunderstanding

0.739

0.574

0.424

High

9

10

Inaccuracy in setting the project schedule

0.734

0.571

0.419

High

10

11

 

Delaying the completion of the paragraphs due to the contractor's lack of financial liquidity

0.737

0.564

0.416

High

11

12

Delayed arrival of materials due to security measures

0.729

0.558

0.407

Medium

12

13

Weak coordination and communication between the employer and the contractor

0.729

0.554

0.404

Medium

13

14

Lack of funding for the project

0.723

0.554

0.401

Medium

14

15

Lack of necessary information (delayed arrival of official correspondence to the work site)

0.731

0.547

0.4

Medium

15

16

Delay in handing over the site to the contractor owing to inadequate site preparation

0.714

0.543

0.388

Medium

16

17

Delay in starting work on the project

0.714

0.54

0.386

Medium

17

18

Damage occurred in some parts of the project

0.714

0.539

0.385

Medium

18

19

Environmental disasters (floods, earthquakes, fires, earthquakes)

0.711

0.541

0.385

Medium

19

20

Due to security incidents, the contractor was unable to receive the site

0.717

0.534

0.383

Medium

20

21

A significant increase in the price of building materials

0.711

0.535

0.38

Medium

21

22

Inflation and price fluctuations during the project implementation period

0.711

0.531

0.378

Medium

22

23

The inability to benefit from the project due to the incompleteness of the project and the issuance of the final acceptance certificate

0.711

0.532

0.378

Medium

23

24

The state owns the project land

0.7

0.527

0.369

Medium

24

25

Delayed completion of designs or change in design

0.7

0.524

0.367

Medium

25

26

Difficulty accessing the site

0.694

0.527

0.366

Medium

26

27

Inaccurate surveys related to the project site by the owner

0.691

0.526

0.363

Medium

27

28

Unclear contractual obligations

0.683

0.519

0.354

Medium

28

29

Delayed approval of executive plans by the

0.68

0.506

0.344

Medium

29

30

Very bad or harsh weather conditions

0.689

0.491

0.338

Medium

30

31

Do religious events and sudden holidays lead to a delay in the project?

0.674

0.5

0.337

Medium

31

32

Disputes during the construction phase between work parties

0.68

0.49

0.333

Medium

32

33

The delay in receiving operational advances according to the contract pending the completion of legal procedures

0.677

0.492

0.333

Medium

33

34

Non-compliance with environmental laws and regulations and their costs

0.683

0.486

0.332

Low

34

35

Switch work location

0.669

0.483

0.323

Low

35

36

Switch work Not allocating a place for throwing rubble location

0.669

0.476

0.318

Low

36

37

The occurrence of internal problems among the contractor team members

0.66

0.464

0.306

Low

37

38

Technical specifications change during the project implementation period

0.654

0.468

0.306

Low

38

39

Delaying procedures for transferring work to the heirs

0.654

0.491

0.294

Low

39

41

the environment surrounding the project

0.651

0.449

0.292

Low

41

42

Work may lead to environmental pollution

0.646

0.451

0.291

Low

42

43

The death of the contractor

0.646

0.439

0.284

Low

43

44

Changing the priorities of the project owner

0.573

0.386

0.221

Very Low

44

Table 9. Greatest risk factors determined by risk score

Rank

Risk Factor

Risk Score

Category Belong

1

Assigning work to an incompetent contractor

0.559

Technical (Related to the contractor)

2

The deterioration of the security situation

0.478

political or security

3

The presence of obstacles at the site (such as groundwater, water pipes, electrical installations... etc.)

0.447

Worksite

4

Occupation of the project by another party leads to a delay in the contractor's receipt of the project

0.445

political or security

5

Unavailability of designs for service networks that cross the location (such as electricity, telephone, water, etc.)

0.442

Organizational

6

Insufficient financial allocations to complete the works

0.437

Financial

7

Late arrival of some materials and equipment from the country of origin

0.435

Technical (Related to the contractor)

8

Mismatch of plans (structural, architectural) or contract documents

0.428

Technical (Related to the contractor)

9

Variations between implementation and needed specifications as a result of plan and specification misunderstanding

0.424

Technical (Related to the contractor)

10

Inaccuracy in setting the project schedule

0.419

Technical (Related to the contractor)

11

Delaying the completion of the paragraphs due to the contractor's lack of financial liquidity

0.416

Financial

12

Delayed arrival of materials due to security measures

0.407

political or security

13

Weak coordination and communication between the employer and the contractor

0.404

Organizational

14

Lack of funding for the project

0.401

Technical (related to the business owner)

15

Lack of necessary information (delayed arrival of official correspondence to the work site)

0.4

Organizational

Figure 9. Most significant risk factors with the risk score

10.3 Groups ranking

Table 10 shows the sources of risks that included several risk factors, divided into eight sources. According to the classification, it is clear that “organizational” risk sources were given priority by the first respondent over others at a rate of (18%), followed by “technical risk factors related to the contractor” at a rate of (17%). It is noted that “risk factors related to the employer, environmental risk factors, and legal risks” had the same percentage (9%), as shown in Figure 10.

Figure 10. Weight of risk source

Table 10. Ranking of overall risk sources

NO.

Risk Source

No. of

Factors

Total RII

Weight

Rank

1

Organizational

8

6.422

18%

1

2

Technical (Related to the contractor)

7

5.86

17%

2

3

Work site

6

4.751

14%

3

4

political or security

5

4.186

12%

4

5

Financial

6

4.057

12%

5

6

Environmental or Natural

4

3.129

9%

6

7

Technical (related to the employer)

4

3.077

9%

7

8

Legal

4

3.077

9%

8

Total

44

34.56

100%

 

11. Conclusion

The primary focus of this research paper was to identify and evaluate the myriad risks impacting projects, utilizing the Statistical Package for Social Sciences (SPSS) for statistical analysis. The results pinpointed the most significant potential risks through a questionnaire technique employed for data collection and evaluation of each identified Risk. Forty-four risk variables were presented and analyzed in this article based on the responses garnered from the questionnaire.

• The risk indicators, based on their risk index/score, were categorized into seven risk sources considering the likelihood and severity of risks and their degree of impact on Iraqi construction tasks during the planning phase.

• The results highlighted the crucial risk elements that warrant consideration during risk management.

1. In most instances, participants and stakeholders in Iraqi construction projects have not adopted risk management methodologies. Hence, the development of a suitable risk management methodology is imperative.

2. A qualitative analysis was conducted to assess the degree of Risk, followed by identifying initial risk variables, encompassing 15 out of the 44 risk categories accountable for risks in Iraqi residential construction projects. The most concerning was "outsourcing work to an incompetent contractor" (RII 55.9%), followed by the deterioration of the security situation (RII 47.8%), and then the presence of obstacles at the site (like groundwater, water pipes, electrical installations, etc.) at (RII 44.7%). The organizational risk factor was the lack of plans for service networks passing through the location (such as electricity, telephone, water, etc.) at (44.2% RII).

3. Various risk factors were classified into seven sources (categories) of Risk, based on their arrangement, revealing "technical (related to contractors), political or security, organizational, financial" as the most significant indicator among other sources of Risk.

• We believe the objective of the risk management process should be to detect, analyze, assess, and prevent the evolution of various risks and associated hazards in a systematic and ongoing manner.

• Expanding the research to develop a model considering threats, hazards, and urgent dangers is essential. Recommendations for future research to enhance risk management in Iraqi construction projects are advisable.

12. Modifications

1. Reorganized the conclusion to summarize key findings, discuss their implications, and finally, provide recommendations for future research, aligning with the reviewer's feedback for a more logical structure.

2. Reframed some sentences to improve clarity and coherence.

3. Segmented information into bullet points and numbered lists for better readability and to address the disjointedness noted by the reviewer.

4. Integrated the suggestion of including recommendations for future research in the last point, emphasizing the necessity of expanded research and improved risk management methodologies for Iraqi construction projects.

  References

[1] Memon, A.H., Rahman, I.A., Azis, A.A.A. (2012). Time and cost performance in construction projects in southern and central regions of Peninsular Malaysia. International Journal of Advances in Applied Sciences, 1(1): 45-52. https://doi.org/10.11591/ijaas.v1i1.537

[2] Cooper, D.F., Grey, S., Raymond, G., Walker, P. (2005). Project Risk Management Guidelines. John Wiley & Sons, Ltd, England. 

[3] Project Management Institute Standard Committee. (2017). A guide to the project management body of knowledge. Sixth edition - Newtown Square Pennsylvania USA PA, p. 397. 

[4] Project Management Institute Standard Committee. (2004). A Guide to the Third Edition of the Project Management Body of Knowledge. Newtown Square Pennsylvania, USA.

[5] Ehsan, N., Mirza, E., Alam, M., Ishaque, A. (2010). Risk Management in construction industry. In 2010 3rd International Conference on Computer Science and Information Technology, Chengdu, China, pp. 16-21. https://doi.org/10.1109/ICCSIT.2010.5564663

[6] Petryshyn, N., Mykytyn, O., Malinovska, O., Khalina, O., Kirichenko, O. (2022). Risk management system at an engineering enterprise in conditions of ensuring security. International Journal of Safety and Security Engineering, 12(4): 525-531. https://doi.org/10.18280/ijsse.120414

[7] Sheen, S.N., Priyan, R.S., Sugumar, S. (2017). A review on risk management in residential projects. International Journal of Engineering Research & Technology (IJERT), 6(11): 295-298.

[8] Aziz, A.A.A., Memon, A.H., Rahman, I.A., Karim, A.T.A. (2013). Controlling cost overrun factors in construction projects in Malaysia. Research Journal of Applied Sciences, Engineering and Technology, 5(8): 2621-2629.

[9] Raftery, J. (1994). Risk Analysis in Project Management. London: New York: E & F.N. Spon.

[10] Mbachu, J., Nkado, R. (2007). Factors constraining successful building project implementation in South Africa. Construction Management and Economics, 25(1): 39-54. https://doi.org/10.1080/01446190600601297

[11] Yoe, C. (2000). Risk analysis frame work for cost estimation. Association with Planning and Management Consultants for U.S. Army Corps of Engineers, Institute of Water Resources, Alexandria.

[12] Flanagan, R., Norman, G. (1993). Risk Management and Construction (2nd Edi.). Oxford.

[13] Rwelamila, P., Lobelo, L. (1997). Factors associated with insolvencies amongst civil engineering construction firms in South Africa. University of Cape Town, Cape Town, South Africa.

[14] Mhetre, K., Konnur, B.A., Landage, A.B. (2016). Risk management in construction industry. International Journal of Engineering Research, 5(1): 153-155. https://doi.org/10.17950/ijer/v5i1/035

[15] Cleland, D.I., Gareis, R. (2006). Global Project Management Handbook: Planning, Organizing, and Controlling International Projects. McGraw-Hill Education. https://doi.org/10.1016/0020-0255(78)90019-1

[16] Kuang, Z. (2010). Risk Management in Construction Projects. Denmark: VIA University College, Horsens Campus, Denmark.

[17] Wang, S.Q., Dulaimi, M.F., Aguria, M.Y. (2004). Risk management framework for construction projects in developing countries. Construction Management and Economics, 22(3): 237-252. https://doi.org/10.1080/0144619032000124689

[18] Edwards, P.J., Bowen, P.A., Hardcastle, C., Stewart, P.J. (2009). Identifying and communicating project stakeholder risks. In Construction Research Congress 2009: Building a Sustainable Future, pp. 776-785. https://doi.org/10.1061/41020(339)79

[19] Hogg, R.V., Tanis, E.A., Zimmerman, D.L. (1977). Probability and Statistical Inference (Vol. 993). New York: Macmillan.

[20] Ibnugraha, P.D., Nugroho, L.E., Santosa, P.I. (2020). Reliability analysis of risk model metrics based on business approach in information security. Ingénierie des Systèmes d’Information, 25(4): 475-480. https://doi.org/10.18280/isi.250410

[21] Xin, L., Rong, W. (2007). Survey research on relationship among service failures, service recovery and customer satisfaction. In 2007 International Conference on Management Science and Engineering, Harbin, China, pp. 1121-1126. https://doi.org/10.1109/ICMSE.2007.4421996

[22] Sambasivan, M., Soon, Y.W. (2007). Causes and effects of delays in Malaysian construction industry. International Journal of Project Management, 25(5): 517-526. https://doi.org/10.1016/j.ijproman.2006.11.007

[23] Mohammed, A.J. (2016). A study for significant risks and their effects on construction projects in Erbil city. Journal of Engineering and Sustainable Development, 20(4): 96-115.

[24] Hamadeh, M., Nayfeh, M., Amodi, O. (2012). Management of construction phase risks for construction projects in Syria. Damascus University Journal for Engineering Sciences.