Optimizing Time in Horizontal Mining Excavations: 10 Formats Inspired by Value Stream Mapping Principles

Optimizing Time in Horizontal Mining Excavations: 10 Formats Inspired by Value Stream Mapping Principles

Johnny Henrry Ccatamayo Barrios* Luis Miguel Soto Jusacamayta Kelvis Berrocal Argumedo Jaime Cesar Mayorga Rojas Walter Javier Díaz Cartagena Roberto-Juan Gutiérrez Palomino H. David Calderón Vilca

Faculty of Mining, Geological and Civil Engineering, Universidad Nacional de San Cristobal de Huamanga, Ayacucho 05001, Peru

Faculty of Geological, Mining, Metallurgical and Geographic Engineering Universidad Nacional Mayor de San Marcos, Lima 07011, Peru

Faculty of Software Engineering, Universidad Nacional Mayor de San Marcos, Lima 07011, Peru

Corresponding Author Email: 
johnny.ccatamayo@unsch.edu.pe
Page: 
517-531
|
DOI: 
https://doi.org/10.18280/jesa.570221
Received: 
5 February 2024
|
Revised: 
2 April 2024
|
Accepted: 
17 April 2024
|
Available online: 
28 April 2024
| Citation

 © 2024 The authors. This article is published by IIETA and is licensed under the CC BY 4.0 license (http://creativecommons.org/licenses/by/4.0/).

OPEN ACCESS

Abstract: 

In this research, 10 formats are proposed as a single instrument, for taking mining cycle times based on the principles of the value chain map tool. As part of the methodology, we applied the 10 proposed formats in time recording, we analyzed the productive, contributory and non-contributory times, for this we used the Ishikawa diagram that shows us which activities have the greatest impact on low productivity in the horizontal excavations (Mining Cycle) later the mapping of the current state was carried out, finally the time efficiency was processed and calculated. To validate the results, we applied the proposal in the Esmeralda mining company, in its El Teniente mine for 4 months. As a result, we revealed that from a total cycle time of 22.85 hours: the productive time was 13.22 hours, the Contributory time was 4.53 hours and non-contributory time was 5.11 hours. We also revealed that the activities that show the lowest performance are: ventilation, marine loading, coining and drilling. The final conclusion is based on the contribution of the 10 formats and is applicable to underground mining companies who can use the 10 proposed formats to analyze productive, contributory and non-contributory times, and then take corresponding actions.

Keywords: 

mining cycle; productivity; performance; value stream mapping, current phase

1. Introduction

The mining industry plays a crucial role in the extraction of minerals and natural resources essential to society [1]. In the context of subway mining operations, it is critical to understand and successfully manage productive times (PT), contributory times (CT) and non-contributory times (NCT). These times represent an integral part of the efficiency and profitability of any mining operation and have a direct impact on mine productivity, safety and profitability [2]. Each time is detailed as follows.

  • Productive times refer to those activities in which the exploitation of horizontal excavations is carried out to prepare and exploit the mine. These activities are important in the mining operation and constitute the main source of income.
  • Contributory times are related to activities of the mining cycle, which although not directly involved, contribute significantly to the mining process, preparation of work fronts, services (water, electricity, fuel, ventilation).
  • Finally, non-contributory times include all activities that do not directly contribute to the main objective of the operation, such as waiting time, idle time or internal transportation.

Effective management of these three types of time is essential to optimize efficiency and ensure safety in subway mining operations.

The application of lean tools is very favorable for organizations, be it productive, commercial or service organizations, since it adjusts to the type of economic activity; it also has easy to understand tools such as; takt time, 5S, Eight wastes, Visual control or management at first sight, Manufacturing Cells, Poka Yoke, Jidoka, Intelligent automation such as, Kaisen, Kanban, SMED, Heijunka TPM or total productive maintenance [3, 4]. However, the Value Stream Mapping (VSM) tool presents significant advantages for evaluating the efficiency of the mining cycle compared to other lean tools. Its ability to offer a comprehensive view of the mining process, identify specific waste, focus on customer value and encourage continuous improvement make it a solid choice. By providing a detailed visual representation of the value stream and encouraging collaboration between teams, VSM is positioned as an effective tool to address the complexities of the mining sector and optimize its operations because the methodology processes are simple. Therefore, in this study “Value Stream Mapping”.

Thus, the Value Stream Mapping (VSM) tool is presented as the appropriate option to establish the real conditions in mining, since it is a good tool to analyze and improve processes in a wide range of industries, allowing a detailed evaluation of production times and the identification of areas for improvement, considering that the optimization of the use of resources is a matter of great importance in the industry in general, being even more demanding in mining and construction [5-7].

The VSM allows a clear and detailed visualization of the production stages and processes involved in the generation of value, which helps to identify areas for improvement and opportunities to increase productivity and reduce production time and costs [8].

On the implementation of lean to improve production times in mining, there are reported cases of implementation in mining development projects [9]. Therefore, this sector is identified as the area that presents the greatest potential for lean implementation in the mining industry through the determination of mining cycle times.

Thus, in the mining industry, the study [10] is analyzed, where a subway mining development project was selected and implemented lean in tunnel excavation works, specifically in the levels of production, sinking, intermediate transport, ventilation and crushing. This implementation was divided into three stages: diagnosis, implementation and control. After analyzing the results of this research, we can indicate that the implementation of lean methods in subway mining development projects in execution has a positive impact on their performance. In particular, the results of this research indicate that the implementation of lean methodologies significantly improve the mean values. On the other hand, the results indicated that the implementation of lean methodologies produces a statistically significant reduction in variability in project performance. Although the results of this application were positive, there are some limitations. Therefore, the addition of other indicators could be considered, such as the behavior of the system in the blasting process, which generates impacts on all the activities of the mining cycle that would allow establishing results of greater impact.

Seifullina et al. [9] analyze a fluorspar mining company of the Votorantim Group, where the mapping of the productive process was performed using TPS concepts and techniques. They indicated that drilling and blasting (together form 45%) are considered essential operations. Preparation (14%) consists of connecting compressed air hoses, among other activities, and is considered an auxiliary operation.

Drill bit sharpening (<1%), change of clothes (2%), travel (10%) and lunch time (5%) are also considered auxiliary operations. Rest time (8%) is an auxiliary operation as it relieves miner fatigue, but is not directly critical to performing the primary operation. Useless operations include waiting (14%) and ventilation (1%), which make up 15% of the operating time performed. It was found that essential drilling and blasting operations were performed individually by the same driller who was responsible for sharpening drill bits and retrieving explosives. This generated downtime of the drilling rig while the driller performed the auxiliary tasks [9].

On the other hand, Lööw [11] presented their research the practice of lean production in mining, where they used idea translation theory. The purpose of their research was to detail how the mining industry has implemented and practiced lean production. The findings suggest that the form and extent of lean production in mining differs from other industries due to the characteristics of the industry. However, there are still blind spots related to the practice that is not reported in the type of material investigated.

Reviewing in the case of the mining company Codelco in the El Teniente Division in the Esmeralda mine regarding mining productivity by applying lean tools, as a result they had not been meeting the expected production, generating low productivity in the activities of the mining cycle, so, they hired the company Green Ingenieria & Consultoria Limitada in 2018, who diagnosed the three main problems that generated delays for the compliance of the effective hours in posture of the mining cycle; being the main activities: equipment handling, manpower and reportability in the mining cycle, directly affecting the 6.3 hrs of work available in posture per shift [12] as a consequence the specialized company has detected that the effective working times in posture per shift are only 4.94 hrs, affecting 21.5% of available work in posture per shift [13] From this previous information, we conducted a study based on interference management, process management and reportability.

The objective of the research is to propose 10 formats based on the principles of the Value Stream Mapping tool: (1) Family of products, (2) Diagram of the current state to determine the efficiency of times in horizontal mining excavations, these formats allow determining the unproductive times or activities in the mining cycle of in a subway mine.

With the proposal, it is possible to identify unproductive times in the mining cycle, the formats lead to a more efficient allocation of available resources. Moreover, operational efficiency is closely linked to cost reduction. The identification and elimination of unproductive times in horizontal mining excavations can contribute significantly to the reduction of operating expenses. All this helps to optimize mining cycle times, allowing more activities to be performed in the same period, which translates into increased productivity and production.

In this context, we will explore in detail how to identify, measure and improve productive times (PT), contributory times (CT) and non-contributory times (NCT) in a subway mine.

This research focuses on the application of the lean philosophy, specifically using its "Value Stream Mapping" (VSM) tool as it allows to evaluate and optimize the productive times in horizontal mining excavations.

2. Materials and Methods

Proposal of 10 formats for time taking in mining cycle activities.

The methodology used in this study for the development of 10 formats for data collection was carried out through the following steps:

Comprehensive analysis of the mining cycle: A detailed study of each stage of the mining process was carried out to identify critical areas, such as operation times, material consumption and operational interferences.

Interdisciplinary collaboration: A multidisciplinary team was formed with mining experts, process engineers and other professionals, integrating diverse perspectives and specialized knowledge in the development of the formats.

Review of best practices and lessons learned: Previous projects were reviewed and best practices in data collection in the mining industry were analyzed to avoid common mistakes and take advantage of lessons learned.

Design of clear and concise formats: Clear and easy-to-complete formats were designed, with specific fields to capture relevant information and guarantee the consistency and accuracy of the data.

Iteration and feedback: An iterative review and feedback process was carried out, where the formats were tested and refined in the field with feedback from users, ensuring their practical usefulness and effectiveness in the field.

Therefore, the final product, the 10 proposed formats, allow the objective of the research to be efficiently addressed.

To apply the proposal of the 10 formats inspired by the Lean methodology in the mining industry in horizontal excavations, (1) Family of products, (2) Diagram of the current state, during the months of August to February 2021, have been considered. The chosen study location was in Chile, Codelco, El Teniente Division, Esmeralda mine-Block Caving exploitation method at the production level, 100 meters from the horizontal excavations, from the Mine Works Management in mining preparation.

2.1 Stage 1 product family

In the development of this proposal adapted to the mining cycle of horizontal excavations, in order to identify the family of products that are subject to evaluation, we propose to carry out the following activities:

  1. Management meeting to address low productivity in mining excavations. All departments involved participate.
  2. Training of the management on the mining cycle and procedures to improve productivity and efficiency.
  3. Selection of a specialized crew to identify and solve the problem of low productivity in the mining field.
  4. Make the instruments to measure what is to be measured, for the case study will be the productive, contributory and non-contributory times of each activity of the mining cycle.

In order to execute the procedures (A, B, C and D), it is important to establish which are the activities that correspond to a mining cycle, as well as the units in which they should be measured, which will be the family of products to be studied.

After having identified the family to be mapped, we proceed to collect all the necessary data to carry out the research, in this case these data correspond to the times of the activities of the mining cycle, this allows us to design the current Value Stream Map.

For this purpose, formats have been proposed, whose contents represent in numbers the activities that are executed to achieve the development of an activity, among which are the activities that generate productive times (PT), contributory times (CT) and non-contributory times (NCT), subsequently in each card the itens (a, b, c) of the percentage of productive times (PT), contributory times (CT) and non-contributory times (NCT) are calculated, in each activity respectively.

This process is composed of a set of activities that follow an orderly, sequential and correlational process that is fulfilled in all the executions of a mining cycle of mining in general, its order goes as follows: ventilation, marine removal, wedging, fortification drilling, bolt grouting, mesh installation, spinning, shotcrete casting, face drilling and explosives loading, from which the productive times (PT), contributory times (CT) and non-contributory times (NCT) times will be calculated.

The time taking formats for each activity require careful measurement to identify the productive, contributory and non-contributory phases, since a series of procedures are carried out for the execution of each activity, such as inspection of the work area, compliance with checklists, crane entry, isolation of the work area, equipment transfer, installation and removal, which are the procedures that generate the contributory times for each activity. On the other hand, the execution of the activity itself represents the net productive time and, added to this, non-contributory times are produced, which represent opportunities for improvement, for which Tables 1-9 are presented as a proposal.

Table 1. Proposed format for time recording in the ventilation activity

Ventilation Emerald Mine Sinking Level and Production-Times in Seconds [s]

Description

Take 01

Take 02

Take N

 

Activity Start time

     
 

Activity End time

     

1

Evaluation of the area to be worked on

     

2

Enabling the work area

     

3

Confinement of the area

     

4

Registration Check list

     

5

Installation of the ventilation duct with crane at 30m from the front of the posture

     

6

Turn on and check the ventilation sleeve

     

7

Gas Level Verification

     

8

Remove Crane

     

a

Productive Times

     

b

Contributory Times

     

c

Non-contributory Times

     
 

Total time in minutes [min]

     

Table 2. Proposed format for time recording in the marine loading activity

Marine Loading Esmeralda Mine Sinking Level and Production-Times in Seconds [s]

Description

Take 01

Take 02

Take N

 

Activity Start time

 

 

 

 

Activity End time

 

 

 

1

Inspection of the work area

 

 

 

2

Registration checklist

 

 

 

4

Confinement of the area

 

 

 

3

Limpieza de marina

 

 

 

4

Limpieza hastiales y zapatera

 

 

 

a

Productive Times

 

 

 

b

Contributory Times

 

 

 

c

Non-contributory Times

 

 

 

Total time in minutes [min]

 

 

 

Table 3. Proposed format for time recording in the wedging activity

Wedging Mina Esmeralda Sinking Level and Production-Times in Seconds [s]

Description

Take 01

Take 02

Take N

 

Activity Start time

 

 

 

 

Activity End time

 

 

 

1

Inspection of the work area

 

 

 

2

Registration checklist

 

 

 

3

Illumination

 

 

 

4

Labor crown wedging machine

 

 

 

5

Labor boxes wedging machine

 

 

 

6

Labor front wedging machine

 

 

 

7

Marking for holding bolts

 

 

 

a

Productive Times

 

 

 

b

Contributory Times

 

 

 

c

Non-contributory Times

 

 

 

 

Total time in minutes [min]

 

 

 

Table 4. Proposed format for time recording in the drilling and bolts activity

Drilling and bolts Mina Esmeralda Sinking Level and Production-Times in Seconds [s]

Description

Take 01

Take 02

Take N

 

Activity Start time

 

 

 

 

Activity End time

 

 

 

1

Inspection of the work area

 

 

 

2

Confinement of the area

 

 

 

3

Registration checklist

 

 

 

4

Positioning Jumbo at the front

 

 

 

5

Water and power installation

 

 

 

6

Water pump installation

 

 

 

7

Bolt drilling

 

 

 

8

Split set drilling

 

 

 

9

Uninstallation of jumbo set and water pump

 

 

 

a

Productive Times

 

 

 

b

Contributory Times

 

 

 

c

Non-contributory Times

 

 

 

Total time in minutes [min]

 

 

 

Table 5. Proposed format for time recording in bolt grouting activity

Bolt grouting Mina Esmeralda Sinking Level and Production-Times in Seconds [s]

Description

Take 01

Take 02

Take N

 

Activity Start time

 

 

 

 

Activity End time

 

 

 

1

Inspection of the work area

 

 

 

2

Registration checklist

 

 

 

3

Crane entry

 

 

 

4

Confinement of the area

 

 

 

5

Transfer of fortification elements

 

 

 

6

Installation of air pump

 

 

 

7

Grouting and bolt placement

 

 

 

9

Jumbo equipment and air pump uninstallation

 

 

 

a

Productive Time [min]

 

 

 

b

Contributory Times [min]

 

 

 

c

Non-contributory Times [min]

 

 

 

Total time in minutes [min]

 

 

 

Table 6. Proposed format for time recording in spinning activity

Spinning Mina Esmeralda Sinking Level and Production-Times in Seconds [s]

Description

Take 01

Take 02

Take N

 

Activity Start time

 

 

 

 

Activity End time

 

 

 

1

Inspection of the work area

 

 

 

2

Registration checklist

 

 

 

3

Crane entry

 

 

 

4

Confinement of the area

 

 

 

5

Spinning

 

 

 

6

Crane removal

 

 

 

a

Productive Times

 

 

 

b

Contributory Times

 

 

 

c

Non-contributory Times

 

 

 

Total time in minutes [min]

 

 

 

Table 7. Proposed format for time recording in shotcrete activity

Shotcrete Mina Esmeralda Sinking Level and Production-Times in Seconds [s]

Description

Take 01

Take 02

Take N

 

Activity Start time

 

 

 

 

Activity End time

 

 

 

1

Inspection of the work area

 

 

 

2

Registration checklist

 

 

 

3

Preparation of projection equipment

 

 

 

4

Water and air installation

 

 

 

5

Mixer checklist registration

 

 

 

6

Mixer installation

 

 

 

7

Confinement of the area

 

 

 

8

Concrete spraying

 

 

 

9

Uninstallation of equipment

 

 

 

a

Productive Times

 

 

 

b

Contributory Times

 

 

 

c

Non-contributory Times

 

 

 

Total time in minutes [min]

 

 

 

Table 8. Proposed format for time recording in face drilling activity

Face Drilling Mina Esmeralda Sinking Level and Production-Times in Seconds [s]

Description

Take 01

Take 02

Take N

 

Activity Start time

 

 

 

 

Activity End time

 

 

 

1

Inspection of the work area

 

 

 

2

Confinement of the area

 

 

 

3

Registration checklist

 

 

 

4

Positioning Jumbo at the front

 

 

 

5

Water and power installation

 

 

 

6

Installation of water pump

 

 

 

7

Drilling

 

 

 

8

Uninstallation of Jumbo equipment and water pump

 

 

 

a

Productive Times

 

 

 

b

Contributory Times

 

 

 

c

Non-contributory Times

 

 

 

Total time in minutes [min]

 

 

 

Table 9. Proposed format for time recording explosive loading activity

Explosive Loading Mina Esmeralda Sinking Level and Production-Times in Seconds [s]

Description

Take 01

Take 02

Take N

 

Activity Start time

 

 

 

 

Activity End time

 

 

 

1

Inspection of the work area

 

 

 

2

Confinement of the area

 

 

 

3

Registration checklist

 

 

 

4

Face drilling untie

 

 

 

5

Evaluation and cleaning of the shots

 

 

 

6

Loading of each shot with crane

 

 

 

7

Detonating cord and safety fuse connection

 

 

 

a

Productive Times

 

 

 

b

Contributory Times

 

 

 

c

Non-contributory Times

 

 

 

Total time in minutes [min]

 

 

 

After the identification of the family of products corresponding to stage 1 of the VSM, it takes time to proceed to execute the methodology for the calculation of productivity indicators in the field. The final indicators are defined as the average obtained from all the measurements taken. Apply the calculation of productivity indicators described below.

 Proceed to calculate the productive, contributory and non-contributory times for each activity of the mining cycle.

Total Cycle Time (TCT): To obtain the total cycle time, the durations in seconds of the horizontal development activities in the shift must be added up.

Productive Time Percentage (PTP): It is calculated as the percentage of time that the productive time TP represents over the total cycle time.

$P T C=\frac{T P}{T C T} * 100$     (1)

Contributory Time Percentage (CTP): It is calculated as the percentage of time represented by the contributory time CT over the total cycle time.

$P T C=\frac{T C}{T C T} * 100$     (2)

Non-Contributory Time Percentage (NCTP): Calculated as the percentage of time represented by non-contributory time NCT over the total cycle time.

$P T C=\frac{T N C}{T C T} * 100$     (3)

Production (P): The yield is calculated by dividing the time of flow units processed by the activity over the man-hours invested.

$\begin{gathered}P=\frac{\text { Activity in linear meters }}{\text { number of operationsxworking hours }} \\ =\mathrm{ml} / \mathrm{HH}\end{gathered}$     (4)

Yield (Y): Yield is calculated by dividing the number of operators per hours worked by the activities in linear meters.

$\begin{gathered}R=\frac{\text { number of operatorsxworking hours }}{\text { activity in linear meters }} \\ =\mathrm{HH} / \mathrm{ml}\end{gathered}$     (5)

Once the results of the productive, contributory and non-contributory times have been established, the Ishikawa diagram should be applied as an instrument as shown in Figure 1, to identify the activities that generate the focus of the problem, using the Ishikawa matrix as a tool that allows us to verify the point of low productivity, which will allow us to carry out stage 2 (Current State Diagram) of the Value Stream Map methodology process.

The Ishikawa analysis helps to identify the root causes of low productivity and high non-contributory times related to the mining cycle, as shown in Figure 2. By addressing these root causes, it allows us to improve the efficiency of operations and reduce the problems associated with low productivity in the mining cycle. This data will be used to apply Table 10, where productive times (PT), contributory times (CT) and non-contributory times (NC) will be determined.

Figure 1. Determination of the focus of the problem

Figura 2. Results of the application of the Ishikawa diagram

After determining the productivity equations and establishing the indicators for each activity, Table 10 is proposed.

Table 10. Control sheet of productive, contributory and non-contributory times

Mining Cycle Activity Times in [%]

Activity

PT%

CT%

NCT%

1

Ventilation

     

2

Marine loading

     

3

Wedging

     

4

Dilling bolt and Split set

     

5

Grouting and bolting

     

6

Spinning of fortification mesh

     

7

Fortification with shotcrete

     

8

Face drilling

     

9

Face loading

     
 

Overall Average Activity

     

The Ishikawa analysis is performed to know what the effect of longer times or lower efficiency is.

To determine which are the activities with the lowest efficiency, we consider the recommendation established by (Vogel, 1996), who maintains that quantitative values of efficiency above 70% are good.

Once stage 1 of the VSM process has been completed, the current state diagram must be executed, having recognized in the first stage the activities that produce lower performance, according to the theory of Vogel, 1996, the reasons that make these activities less productive must then be established graphically.

In order to facilitate a deeper understanding of value chain maps in the context of the mining industry, a valuable tool is presented: an adaptation of the value chain mapping scheme developed by Porter in 1985.

This version emphasises the usefulness of the instrument and highlights its value to better understand value chain maps in the mining industry, taking into account Table 11, we proceed to construct the value chain map (VSM) to execute the development of the proposal.

Using Table 11, it is recommended to execute the current state value chain map.

Table 11. Symbology for the construction of value chain maps

Symbol

Name

Meaning

External agent

Represents a supplier or customer.

Activity

Represents an activity processing units.

Pushed flow

Represents units being driven by the production of an activity.

Supermarket

Represent kanban supermercad.

Inventory

Represents the inventory.

Production control

Represents the entity in control of production.

Manual information

Represents the flow of information by manual means.

Timeline

It shows in its valleys the time of activity that add value and in the moments in which they do not.

Data box

Contains the indicators corresponding to the activity.

Transportation

Represents the transportation of material from an off-site location to the job site.

Retirement Kanban

Represents the flow of retirement kanban cards.

Kaizen Event

Represents a kaizen event and the improvements to be implemented.

Operator

Represents a worker performing an activity.

3. Results

The validation of our proposed formats, based on the principles of the Value Stream Mapping tool, has proven to be highly effective in assessing and improving time efficiency in horizontal mining excavations. This innovative approach has been tested in a real environment, at the Esmeralda mine, in its El Teniente division located in the southern country of Chile.

In this validation process, we have had the collaboration of Geovita S.A., a company specialized in the execution of subway works, excavations with their associated fortifications, assemblies and civil works associated with mining, road and hydroelectric projects, responsible for the management of the activities related to the mining cycle in the El Teniente Mine. The experience and knowledge provided by Geovita have been fundamental to ensure the success and applicability of our proposal.

Our 10-format proposal, supported by the Value Stream Mapping methodology, offers a comprehensive and effective approach to evaluate and optimize horizontal mining excavation processes. The results of this validation highlight the relevance and feasibility of implementing these practices in the mining industry, paving the way towards greater efficiency and productivity in horizontal mining operations.

3.1. Results of stage 1 product family

Table 12. Family of products to be mapped

Description

1

Ventilation

2

Marine withdrawal

3

Wedging

4

Drilling, fortification and split set

5

Bolt grouting

7

Spinning

8

Shotcrete

9

Face drilling

10

Loading

To show the results of the research carried out, the first stage is the identification of families, considering these as all the activities of the mining cycle at El Teniente mine, as shown in Table 12.

In accordance with Table 12, having identified the family of products, we proceeded to take the average times of each activity, using the proposals in Table 1, having as acronyms Nv-H: Sinking Level, C: Crossing, Rap: Ramp and XC: Access. On the other hand, the format should consider, as a fundamental summary of the data collection, the productive times (PT), contributory times (CT) and non-contributory times (NCT), obtaining the following results, which are shown in Tables 13-22.

Table 13. Time taking of each activity in the ventilation

Format N° 1: Esmeralda Mine Ventilation-Sinking and Production Level-Times in Seconds [s]

Description

Take 01

Take 02

Take 03

Take 04

Take 05

Take 06

Take 07

 

Date and Working Level

06-Oct Nv-H

07-Oct Nv-H

07-Oct Nv-H

08-Oct Nv-H

08-Oct Nv-H

08-Oct Nv-P

08-Oct Nv-P

Labor

C-27 Sur XC-5

C-43 Sur Acc-5

Rap N°2 FW

XC Acc 6 HW C31

XC Acc 6 FW C31

Z-47 al Fw C-55

Z-50 al FW C-43

 

Activity Start Time

10:32 a.m

11:01 a.m

11:05 a.m

10:58 a.m

12:20 p.m

10.30 a.m

12:00 p.m.

Activity End Time

11:31 a.m

12:10 p.m

12:41 p.m

12:11 p.m

1:19 p.m

11:49 a.m

1:20 p.m

1

Evaluation the area to be worked

312

321

362

248

456

543

664

2

Enabling the work area

111

128

109

126

105

129

134

3

Confinement of the area

240

232

432

476

254

465

345

4

Registration Checklist

308

301

356

461

351

475

321

5

Installation of the chute with crane at 30m from the front of the posture

1680

1870

1768

1587

1654

1598

1653

6

Start-up and verification of the ventilation sleeve

178

184

176

187

174

165

179

7

Gas Level Check

79

99

100

100

94

122

204

8

Remove Crane

100

72

98

165

145

76

64

a

Productive Times

30.97

34.23

32.40

29.57

30.47

29.38

30.53

b

Contributory Times

19

19

24

26

23

30

29

c

Non-Contributory Times

99

106

130

108

96

110

111

 

Total time in minutes [min]

148.97

159.23

186.4

163.57

149.47

169.38

170.53

Table 14. Time taking of each activity in the marine loading

Formato N° 2: Marine Loading Esmeralda Mine Sinking and Production Level-Times in Seconds [s]

Description

Take 01

Take 02

Take 03

Take 04

Take 05

Take 06

Take 07

Take 08

Take 09

Take 10

 

Date and Work Level

06-Oct Nv-H

06-Oct Nv-H

07-Oct Nv-H

07-Oct Nv-H

07-Oct Nv-H

07-Oct Nv-P

07-Oct Nv-P

07-Oct Nv-P

07-Oct Nv-P

08-Oct Nv-H

 

Labor

C-27 Sur XC-5

 XC-Acc 6 HW C31

C-45 Norte Acc-5

C-43 Sur Acc-5

 C-29 Sur XC-5

C-43 al Sur Z40

C-47 al Sur Z-49

C-51 al Sur Z-44

Z-41 al HW C-45

C-27 SUR XC-5

 

Activity Start Time

11: 33 a.m

4:16 p.m

1:25 a.m

3:56 p.m

11:15 a.m

11:30 a.m

6:00 p.m

2:10 p.m

11:00 a.m

10:45 a.m

 

Activity End Time

1:50 p.m

6:32 p.m

4:02 a.m

6:38 p.m

1:31 p.m

1:44 p.m

11:30 p.m

5:29 p.m

1:31 p.m

1:02 p.m

1

Inspection of area to be worked

286

465

589

318

468

267

426

589

251

735

2

Registration checklist

256

356

578

538

398

254

631

559

243

438

4

Isolation of area to be worked

258

185

325

345

314

251

247

231

256

315

3

Marine cleaning

4318

4692

5201

5295

5612

4753

6528

6834

4893

4867

4

Gable cleaning

356

356

532

467

678

754

867

610

659

437

a

Productive Times

77.9

84.1

95.6

96.0

104.8

91.8

123.3

124.1

92.5

88.4

b

Contributory Times

13.3

16.8

24.9

20.0

19.7

12.9

21.7

23.0

12.5

24.8

c

Non-Contributory Times

46

36

30

36

12

30

70

52

46

24

Total time in minutes [min]

137.2

136.9

150.5

152

136.5

134.7

215

199.1

151

137.2

Table 15. Time taking of each activity in the wedging

Format N° 3: Wedging Esmeralda Mine Sinking Level and Production-Times in Seconds [s]

Description

Take 01

Take 02

Take 03

Take 04

Take 05

Take 06

Take 07

Take 08

Take 09

Take 10

 

Date and Work Level

06-Oct Nv-H

06-Oct Nv-H

06-Oct Nv-H

07-Oct Nv-H

07-Oct Nv-H

07-Oct Nv-P

07-Oct Nv-P

07-Oct Nv-P

07-Oct Nv-P

07-Oct Nv-P

 

Labor

Calle 29 Sur XC-5

C-27 Sur XC-5

XC-Acceso 6 HW C31

C-43 Sur Acc-5

C-29 Sur XC-5

C-43 al Sur Z40

C-47 al Sur Z-49

C-51 al Sur Z-44

Z-41 al HW C-45

C-45 Norte Acc-5

 

Activity Start Time

11:44 a.m

04:42 p.m

09:32 p.m

09:27 p.m

02:57 p.m

9.00 p.m

1:30 a.m.

05:31 p.m

02:45 p.m

10:30 p.m

 

Activity End Time

1:02 a.m

06:32 p.m

11:09 p.m

11:34 p.m

4:19 p.m

10:34 p.m

3:19 a.m

06:50 p.m

04:10 p.m

11:56 p.m

1

Inspection of area to be worked

290

327

312

586

456

435

534

603

299

664

2

Registration checklist

456

600

345

335

312

543

421

487

357

478

3

Illumination

376

399

235

345

301

465

356

365

256

301

4

Wedging of the crown of the work

1086

1756

1767

2357

1156

1647

2523

1075

1059

1156

5

Wedging of the boxes of the work

796

913

974

1398

846

832

803

834

768

829

6

Wedging of the work face

178

879

567

900

699

443

350

412

301

456

7

Marking for Holding bolts

524

697

660

458

567

479

436

376

587

476

a

Productive Times

43

71

66

85

54

57

69

45

45

41

b

Contributory Times

19

22

15

21

18

24

22

24

15

24

c

Non-Contributory Times

16.5

18.2

17

21

9

13

19

11

25

21.3

 

Total time in minutes [min]

78.5

111.2

98

127

81

94

110

80

85

86.3

Table 16. Time taking of each activity in the bolt drilling and split set

Format N° 3: Wedging Esmeralda Mine Sinking Level and Production-Times in Seconds [s]

Description

Take 01

Take 02

Take 03

Take 04

Take 05

Take 06

Take 07

Take 08

Take 09

Take 10

 

Date and Work Level

06-Oct Nv-H

06-Oct Nv-H

06-Oct Nv-H

06-Oct Nv-H

06-Oct Nv-P

06-Oct Nv-P

06-Oct Nv-P

07-Oct Nv-P

07-Oct Nv-P

07-Oct Nv-H

 

Labor

C-29 Sur XC-5

C-27 Sur XC-5

XC Acc 6 HW C31

XC Acc 6  FW C31

Z-47 al Fw C-55

Z-50 al HW C-43

Z-50 al Hw C-47

C-43 Sur Acc-5

C-29 Sur XC-5

C-43 al Sur Z40

 

Activity Start Time

2:15 p.m

9:30 p.m

1:30 a.m

10:30 a.m

3:00 p.m.

10:45 a.m

10:45 a.m

12:45 a.m

3:46 p.m

10:45 p.m

 

Activity End Time

5:29 p.m

12:24 a.m

7:33 a.m

1:30 p.m

5:47 p.m

1:38 p.m

2:14 p.m

3:48 a.m

8:16 p.m

2:22 a.m

1

Inspection of the area to be worked

211

387

701

357

342

587

482

435

304

265

2

Isolation of area to be worked

160

321

253

231

169

357

287

300

264

275

3

Registration checklist

389

489

314

438

320

302

652

381

536

303

4

Positioning Jumbo in front

124

176

128

176

156

178

247

171

124

176

5

Power and water installation

246

470

587

356

456

359

536

351

467

547

6

Installation of water pump

186

238

125

438

240

175

235

235

306

303

7

Drilling Bolts

7000

7452

8363

6951

8000

6202

7253

7318

6335

8913

 

Jumbo equipment and water pump

851

768

1062

827

972

925

872

930

798

900

 

uninstallation

a

Productive Times

139.9

148

164.1

138.6

154.5

127.8

148.4

148.5

128.9

173.6

b

Contributory Times

20.2

30.5

39.1

35.2

25.1

30.9

35.7

25

30.5

25.6

c

Non-Contributory Times

34

25

160

21.3

0

14

20

10

10

18

 

Total time in minutes [min]

194.1

203.5

363.2

195.1

179.6

172.7

204.1

183.5

169.4

217.2

Table 17. Time taking of each activity in the bolt grouting

Format N° 5: Bolt grouting Esmeralda Mine Sinking Level and Production-Times in Seconds [s]

Description

Take 01

Take 02

Take 03

Take 04

Take 05

Take 06

Take 07

Take 08

Take 09

Take 10

 

Date and Work Level

06-Oct Nv-H

06-Oct Nv-H

06-Oct Nv-P

06-Oct Nv-P

06-Oct Nv-P

06-Oct Nv-P

07-Oct Nv-H

07-Oct Nv-H

07-Oct Nv-H

07-Oct Nv-P

 

Labor

Calle 29 Sur XC-5

XC Acceso  6  FW C-31

C-43 al Sur Z-40

Z-47 al Fw C-55

Z-50 al HW C-43

Z-50 al Hw C-47

C-29 Sur XC-5

C-27 Sur XC-5

XC Acc 6 HW C31

C-51 al Sur Z-44

 

Activity Start Time

5:45 p.m

1:15 a.m

11:44 a.m

9:00 p.m

1:45 p.m.

4:30 p.m

8:45 p.m

12:34 p.m

10:30 a.m

1:30 a.m

 

Activity End Time

6:58 p.m

2:48 a.m

1:16 p.m

11:16 p.m

3:58 a.m

6:33 p.m

10:42 p.m

2:43 p.m

12:15 a.m

3:19 a.m

1

Inspection of the area to be worked

246

287

295

242

254

305

246

240

243

307

2

Registration checklist

600

686

543

487

587

654

487

480

308

278

3

Crane entry

154

186

134

68

132

132

126

136

187

125

4

Isolation of the area to be worked

142

128

125

134

97

67

186

245

125

79

5

Transfer of fortification elements

196

243

301

187

364

125

302

78

312

181

6

Instalation of air pump

184

301

183

128

183

247

182

183

189

129

7

Grouting and bolt installation

3632

3180

3648

5879

4321

5659

3354

3967

3801

3640

8

Uninstallation of jumbo equipment and air pump

246

184

300

185

243

185

297

300

301

360

a

Productive times [min]

70.5

68

65.8

101

79

101.3

63.9

73.1

70.4

64.7

b

Contributory times [min]

19.5

18.6

26.4

20.9

24

21.6

25.4

20.7

20.7

20.3

c

Non-contributory times [min]

0

7

0

14

30

0

6

0

14

24

Total time in minutes [min]

90.0

90

93.6

92.2

135.8

133

122.9

95.3

93.8

105.1

Table 18. Time taking of each activity in the mesh

Format N° 6: Mesh Esmeralda Mine Sinking Level and Production - Times in Seconds [s]

Description

Take 01

Take 02

Take 03

Take 04

Take 05

Take 06

Take 07

Take 08

Take 09

Take 10

 

Date and Work Level

06-Oct Nv-H

06-Oct Nv-H

06-Oct Nv-P

06-Oct Nv-P

06-Oct Nv-P

06-Oct Nv-P

07-Oct Nv-H

07-Oct Nv-H

07-Oct Nv-H

07-Oct Nv-H

 

Labor

C-45 Norte Acc-5

C-29 Sur XC-5

C-43 al Sur Z-40

C-47 al Sur Z-49

C-51 al Sur Z-44

Z-50 al Hw C-47

C-29 Sur XC-5

C-27 Sur XC-5

XC Acc 6 HW C31

XC Acc 6 FW C31

 

Activity Start Time

12:14 p.m

9:41 p.m

5:00 p.m

2:30 p.m

10:45 a.m.

9:46 p.m

1:30 a.m

9:00 p.m

2:30 p.m

4:30 p.m

 

Activity End Time

1:35 p.m

11:17 p.m

6:34 p.m

4:04 p.m

12:46 p.m

11:18 p.m

3:58 a.m

10:16 p.m

4:26 p.m

6:30 p.m

1

Inspection of the area to be worked

178

76

321

246

368

246

305

162

241

300

2

Registration checklist

244

360

284

227

368

245

427

286

346

583

3

Crane entry

124

186

243

125

128

121

185

126

183

124

4

Isolation of the area to work

68

85

74

85

46

60

83

65

81

80

5

Mesh preparation

485

547

600

426

542

368

543

261

200

542

6

Laying of mesh

2687

3603

3125

3441

5808

3403

5742

3201

4625

3634

7

Crane removal

246

254

185

363

246

247

186

168

184

126

a

Productive Times

58.8

70.1

65.1

61.4

100.8

59.7

100.7

60.4

107.1

80.6

b

Contributory Times

10.4

15.1

15.5

20.5

24.3

18.5

25.8

10.8

10.6

9.3

c

Non-Contributory Times

16

14

24

13

0

17

24

10

15

30

Total time in minutes [min]

85.20

99.20

104.60

94.90

125.10

95.20

150.50

81.20

132.70

119.90

Table 19. Time taking of each activity in the spinning

Format N° 7: Spinning Esmeralda Mine Sinking Level and Production-Times in Seconds [s]

Description

Take 01

Take 02

Take 03

Take 04

Take 05

Take 06

Take 07

Take 08

Take 09

Take 10

 

Date and Work Level

06-Oct Nv-H

06-Oct Nv-H

06-Oct Nv-H

06-Oct Nv-P

06-Oct Nv-P

06-Oct Nv-P

06-Oct Nv-P

06-Oct Nv-P

07-Oct Nv-H

07-Oct Nv-H

 

Labor

C-45 Norte  Acc-5

C-43 Sur Acc-5

C-29 Sur XC-5

C-43 al Sur Z-40

C-47 al Sur Z-49

C-51 al Sur Z-44

Z-50 al FW C-43

Z-50 al Hw C-47

C-27 Sur XC-5

XC Acc 6 HW C31

 

Activity Start Time

2:30 p.m

10:30 a.m

12:17 a.m

10:00 p.m

4:42 p.m.

2:30 p.m

12:47 a.m

3:30 a.m

11:30 p.m

4:30 p.m

 

Activity End Time

4:37 p.m

12:28 p.m

2:27 a.m

11:32 p.m

6:58 p.m

4:38 p.m

2:31 a.m

5:17 a.m

1:41 a.m

6:45 p.m

1

Inspection of the area to be worked

120

246

365

300

426

306

367

194

256

367

2

Registration checklist

368

486

543

320

295

486

438

539

603

663

3

Crane entry

69

73

84

185

125

180

174

121

198

185

4

Isolation of the area to work

67

185

123

239

126

175

84

68

125

180

5

Spinning

4647

5364

5678

3403

5080

5390

3880

3529

5607

5626

6

Crane removal

185

245

185

119

301

245

309

176

234

297

a

Productive Times

83.5

95.4

100.6

63.7

91.7

94.8

70.7

64.8

96.5

100.8

b

Contributory Times

7.5

14.6

15.7

12.4

14.2

18.2

16.9

12.3

20.6

21.2

c

Non-Contributory Times

36

7

14

16

30

15

17

30

14

13

Total time in minutes [min]

126.9

117.0

130.3

92.1

135.9

128.0

104.5

107.1

131.1

135.0

Table 20. Time taking of each activity in the shotcrete

Format N° 8: Shotcrete Esmeralda Mine Sinking Level and Production-Times in Seconds [s]

Description

Take 01

Take 02

Take 03

Take 04

Take 05

Take 06

Take 07

Take 08

Take 09

Take 10

 

Date and Work Level

06-Oct Nv-H

06-Oct Nv-H

06-Oct Nv-H

06-Oct Nv-P

06-Oct Nv-P

06-Oct Nv-P

06-Oct Nv-P

06-Oct Nv-P

07-Oct Nv-H

07-Oct Nv-H

 

Labor

C-45 Norte Acc-5

C-43 Sur Acc-5

C-29 Sur XC-5

C-43 al Sur Z-40

C-47 al Sur Z-49

C-51 al Sur Z-44

Z-41 al HW C-45

Z-50 al Hw C-47

C-27 Sur XC-5

XC Acc 6 HW C31

 

Activity Start Time

5:45 p.m.

1:03 p.m

2:30 a.m

1:00 a.m

10:00 p.m

4:45 p.m.

10:45 a.m

6:00 a.m

1:44 a.m

8:00 p.m

 

Activity End Time

7:01 p.m

2:44 p.m

4:13 a.m

2:32 a.m

12:00 a.m

6:30 p.m

12:18 p.m

7:42 a.m

3:28 a.m

10:00 p.m

1

Inspection of the area to be worked

537

421

778

472

598

486

547

483

427

486

2

Robot registration checklist

365

389

542

386

600

347

427

300

338

544

3

Projection equipment preparation

130

123

221

287

242

562

202

363

220

662

4

Water and air installation

101

275

243

114

104

203

143

153

143

226

5

Mixer registration checklist

104

165

210

124

163

265

153

147

153

245

6

Mixer installation

132

176

246

185

243

180

185

237

178

245

7

Isolation of the area to work

237

195

276

156

173

168

164

132

124

115

8

Concrete spraying

2759

2646

2635

2143

3264

3001

2954

3921

3728

3603

9

Uninstallation of equipment

175

165

135

210

185

153

276

143

265

246

a

Productive Times

75.7

72.1

70.9

72

72.4

75

69.2

77.4

77.9

86.1

b

Contributory Times

10

15.8

23.2

18

26.5

20.4

15

27.6

20

23.2

c

Non-Contributory Times

10

10

10

10

12

10

12

10

10

10

Total time in minutes [min]

95.7

97.9

104.1

100.0

110.9

105.4

96.2

115.0

107.9

119.2

Table 21. Time taking of each activity in the face drilling

Format N° 9: Face drilling Esmeralda Mine Sinking Level and Production-Times in Seconds [s]

Description

Take 01

Take 02

Take 03

Take 04

Take 05

Take 06

Take 07

Take 08

Take 09

Take 10

 

Date and Work Level

06-Oct Nv-H

06-Oct Nv-H

06-Oct Nv-H

06-Oct Nv-P

06-Oct Nv-P

06-Oct Nv-P

06-Oct Nv-P

07-Oct Nv-H

07-Oct Nv-H

07-Oct Nv-H

 

Labor

C-45 Norte Acc-5

C-43 Sur Acc-5

C-29 Sur XC-5

C-43 al Sur Z-40

C-47 al Sur Z-49

C-51 al Sur Z-44

Z-41 al HW C-45

C-27 Sur XC-5

XC Acc 6 HW C31

XC Acc 6 FW C31

 

Activity Start Time

9:30 p.m

3:15 p.m

4:27 a.m

2:45 a.m

1:00 a.m

9:16 p.m.

2:30 p.m

3:45 a.m

11:00 a.m

1:31 a.m

 

Activity End Time

12:46 p.m

7:18 p.m

7:30 a.m

5:42 a.m

4:16 a.m

12:45 p.m

6:28 p.m

7:02 a.m

2:29 a.m

4:43 a.m

1

Inspection of the area to be worked

374

236

397

0

423

335

424

0

413

0

2

Isolation of the area to work

236

425

309

325

287

300

365

426

365

236

3

Registration checklist

415

436

486

432

481

433

473

413

472

532

4

Positioning Jumbo to the front

413

364

246

286

543

421

368

325

304

308

5

Power and water installation

683

545

584

513

634

546

524

558

534

553

6

Water pump installation

302

359

236

181

287

148

252

167

365

243

7

Drilling

7066

8839

7336

7294

7255

7067

7564

7381

7396

7788

8

Jumbo equipment and water pump uninstallation

273

285

248

225

236

282

368

243

386

238

a

Productive Times

117.8

147.3

122.3

121.6

120.9

117.8

126.1

123.0

123.3

129.8

b

Contributory Times

44.9

44.2

41.8

32.7

48.2

41.1

46.2

35.5

47.3

35.2

c

Non-Contributory Times

33

52

20

23

27

50

66

39

38

27

Total time in minutes [min]

195.7

243.5

184.0

177.3

196.1

208.9

238.3

197.6

208.6

192.0

Table 22. Time taking of each activity in the explosive loading

Format N° 10: Explosive Loading Esmeralda Mine Sinking Level and Production-Times in Seconds [s]

Description

Take 01

Take 02

Take 03

Take 04

Take 05

Take 06

Take 07

Take 08

Take 09

Take 10

 

Date and Work Level

06-Oct Nv-H

06-Oct Nv-H

06-Oct Nv-P

06-Oct Nv-P

06-Oct Nv-P

07-Oct Nv-H

07-Oct Nv-H

07-Oct Nv-P

07-Oct Nv-P

07-Oct Nv-P

 

Labor

C-45 Norte Acc-5

C-43 Sur Acc-5

C-43 al Sur Z40

C-51 al Sur Z-44

Z-41 al HW C-45

XC Acceso 6HW C31

XC Acceso 6 FW C31

Z-47 al Fw C-55

Z-50 al HW C-43

Z-50 al Hw C-47

 

Activity Start Time

1:45 a.m

5:15 a.m

6:00 a.m

4:45 a.m

1:30 a.m

3:30 a.m.

5:30 a.m

1:30 a.m

3:45 a.m

10:00 p.m

 

Activity End Time

3:32 a.m

6:44 a.m

7:32 a.m

6:32 a.m

2:48 a.m

5:28 a.m

7:27 a.m

3:16 a.m

5:28 a.m

11:43 p.m

1

Inspection of the area to be worked

485

225

357

237

372

295

243

299

301

304

2

Isolation of the area to work

85

106

82

53

47

43

78

101

78

126

3

Registration checklist

344

486

348

387

377

360

367

331

376

343

4

Face drilling untie

165

0

264

0

574

754

0

487

0

0

5

Evaluation and cleaning of the shots

184

207

241

125

0

279

154

127

0

0

6

Loading of each shot with crane

4441

3710

3147

4321

3993

4585

4594

3856

3743

4401

7

Detonating cord and safety fuse connection

397

320

496

798

837

495

659

713

845

720

a

Productive Times

80.6

67.2

60.7

85.3

80.5

84.7

87.6

76.2

76.5

85.4

b

Contributory Times

21.1

17.1

21.5

13.4

22.8

28.9

14.0

22.4

12.6

12.9

c

Non-Contributory Times

6

5

10

9

5

6

6

8

14

5

Total time in minutes [min]

107.7

89.2

92.3

107.7

108.3

119.5

107.6

106.6

103.1

103.2

As shown in Tables 13-22 of the proposed format, times have been taken for each activity that makes up the mining cycle, which allows first validating the format and then establishing the results of the productive, contributory and non-contributory times shown in indicators a, b and c at the end of each table, which allows to establish the real times of the mining cycle and compare them with the standard times of the contract.

3.2. Results of stage 2 current state diagram

To present the results of the current state analysis, initially the Ishikawa diagram tool was used, which allowed to clearly identify the activities that are contributing to the low productivity problems.

Therefore, the Ishikawa tool adapted to the context of the Esmeralda mine was applied.

The first action consisted of carrying out an exhaustive field review with a specialized team composed of three Lean Manufacturing experts, three shift leaders, six foremen and a superintendent. During this field phase, several irregularities were detected related to mine personnel, work methods, equipment condition, post-dumping aspects of the material, spaces available for the placement of marinas and mine site management standards.

The analysis revealed that, due to the aforementioned reasons, personnel are not performing their tasks in a standardized manner. In addition, the lack of mechanical personnel at the fronts was confirmed and it was verified that adequate training has not yet been provided to the personnel. Regarding methods, a problem was identified in the distribution of drilling mesh. Regarding equipment, the presence of inoperative equipment was observed. In relation to the material, an excess of marina was observed in comparison with the quantities established in the contract by the mine works management, generating problems in the availability of shafts for the placement of the marina. Finally, with regard to the sections defined in the contract, it was found that these exceeded the proposed value by %, this being the main cause of an over-excavation of 30%, exceeding the limits established by the mine works management, which originally proposed only 12%.

In the Ishikawa analysis it was possible to identify that four activities of the mining cycle (Ventilation, marine loading, wedging, face drilling) represent the focus of the problem of low productivity since they have longer or less efficient times, so the problem should be attacked considering only the improvement in these activities, taking into account the following reasons:

Personnel: The work procedures of the different activities are not controlled, generating inadequate procedures that are not noticed by the (technical site inspectors), so there are activities that exceed the standardized limits, resulting in over-excavations that generate more time in the wedging.

Equipment: The equipment is not repaired quickly because they do not have good logistics for the purchase of parts. The low voltage of the electrical power causes damage to the electrical box of the postures and the Jumbo box, which takes a long time because the procedure indicates that the electrician must be called to solve this problem (there are only two electricians for the two levels, sinking and production). The jumbo does not comply with preventive maintenance because the shift manager is responsible for delivering the equipment to the mechanical shop and this is not done.

The re-handling of materials causes more traffic of the Scoop Equipment having sawed postures by marine traffic and this generates interference, the marine stockpiling is done by the specialized company Geovita because of the need to continue blasting without thinking that it generates interference in the area by the transfer of the Scoop equipment. The biggest problem is the availability of rock chips, which is the responsibility of the mining company.

Method: The drilling mesh is designed for only a section size of 4.0m x 4.5m and does not change the drilling pattern which depends on the type of rock and explosive. The method has a lot of interference because of the 38 pieces of equipment that are moved by the two main positions, these are mining and civil works equipment plus the Mixer that supplies the two processes.

Material: Over-excavation generates a greater amount of: marine, split set, helical bolts, Shotcrete, equipment and time that are associated with building larger excavations. Civil works have a greater problem since over-excavation causes a greater consumption of concrete that is used in road surfaces, extraction points and confining walls.

All the described processes culminate in the main cause of the problem, which is the over excavation that generates the low yields, due to the fact that ventilation, marine loading, wedging and face drilling have a significant influence on these results, which are validated by measuring the execution times of the construction processes of the horizontal excavations described in stage 1.

In this research, we contextualise the activities with the lowest performance based on the results found in the calculation of performances carried out in the time taking in the previous stage, leaving Tables 23, 24, and Figure 3 as a tool adapted to the mining cycle of horizontal excavations.

From Tables 23, 24 and Figure 3, the main activities that generate the greatest delays have been identified as the families involved. The activities in the mining cycle must achieve at least 70% of productive work, and it can be seen that the activities that do not achieve this performance are ventilation with 18.96% productivity, marine loading with 63.13%, wedging with 60.57% and face drilling with 61.2%.

Table 23. Results of mining cycle averaging in minutes

Average Process Times in Minutes [min]

Activity

PT

CT

NCT

TCT

Ventilation

31.1

24.3

108.6

164

Marine loading

97.85

18.96

38.2

155.01

Wedging

57.6

20.4

17.1

95.1

Bolt and Split set drilling

147.23

29.78

31.23

208.24

Bolt grouting

75.77

21.81

9.5

107.08

Mesh laying

76.47

16.08

16.3

108.85

Spinning

86.25

15.36

19.2

120.81

Shotcrete

74.87

19.97

10.4

105.24

Face drilling

125

41.71

37.5

204.21

Explosive loading

78.47

18.67

7.4

104.54

Table 24. Results of process averaging in minutes

Summary of Average Times in [%]

Actividad

PT%

CT%

NCT%

Ventilation

18.96

14.81

66.23

Marine loading

63.13

12.23

24.64

Wedging

60.57

21.45

17.98

Bolt and Split set drilling

70.7

14.3

15

Bolt grouting

70.76

20.37

8.87

Mesh laying

70.25

14.77

14.98

Spinning

71.4

12.7

15.9

Shotcrete

71.14

18.98

9.88

Face drilling

61.2

20.4

18.4

Explosive loading

75.1

17.8

7.1

Average

63.32

16.78

19.90

Figure 3. Identification of underperforming activities

In Figure 4, the maps of the current state of the value chain of the low performance activities (marine loading, wedging and face drilling) are constructed and presented, ventilation is a consequence of some activities and materials, which is why it will only be analyzed at the end, where the times assigned to each activity to perform the work in the positions are shown in detail, quantifying the % of Productive Time and the % of Contributory Time, separating these from Non-Contributory Time.

Figure 4 shows in detail the times assigned to each activity to perform the work in the positions, quantifies the % of Productive Time and % of Contributory Time, separating these from Non-Contributory Time.

When elaborating the current state map, it is immediately identified that the complete realization of the activities requires long periods of time, the total cycle time is 22.1 hours, as calculated in Figure 4 of the current state diagram. The time that does not add value is 5.3 hours, speaking only of the productive work hours. The statistical pie chart indicates the efficiency in percentage of compliance, being green the percentage of productive time, yellow the percentage of time that contributes to the activity and red the percentage of non-contributory time.

Figure 5 shows that the times established in the contract are not related to the times found when applying the current V.S.M., due to the fact that at the time of making the contract, the existence of operational interferences that are an important factor in the determination of the real yields is not taken into account, added to the fact that only a value of 19% of over excavation is considered while in reality an over excavation of 32% has been calculated, which generates operational increases in the mining cycle.

Figure 4. VSM of Horizontal Developments Current status of all activities in the mining cycle of horizontal excavations

Figure 5. Identification of the times in the current VSM/Contract mining cycle

4. Conclusions

In this study, the importance and effectiveness of the application of the 10 formats designed for data collection in all activities of the mining cycle has been demonstrated. These formats have made it possible to collect detailed and precise information on the times of each activity, providing a comprehensive and updated vision of the entire mining process.

The results found during the application of these formats have been revealing. It was possible to accurately determine the productive (13.22 hours), contributory (4.53 hours) and non-contributory (5.11 hours) times in the different stages of the mining cycle. This time segmentation has provided a deeper understanding of operational efficiency, highlighting specific areas that require attention.

The use of these formats has also made it possible to compare the times obtained with those established in the contracts or production objectives. This comparison has revealed significant discrepancies in key activities such as venting (18.96%), marine loading (63.13%), coining (60.57%) and drilling (61.2%). These findings highlight the importance of strategically addressing underperforming areas to improve the overall efficiency of the mining cycle.

Furthermore, the application of the Ishikawa tool to analyze the collected data has been essential to identify the root causes of the identified problems. It was determined that overexcavation, caused by the use of certain explosives, is the main cause that affects productivity. These results provide a solid foundation for implementing corrective and strategic actions that directly address the identified challenges.

Finally, the results found during the application of the 10 formats for data collection in all activities of the mining cycle underline its value as a powerful tool to collect real data, identify areas of improvement and make informed decisions to optimize the mining process. Its systematic and rigorous application is essential to guarantee efficient and competitive management in the mining industry.

To ensure the efficiency and continued success of this approach, it is essential to approach the analysis from a global perspective, integrating data collection continuously into all daily operational reports, from excavations to management. This involves establishing a robust, automated information system that allows conditions and performance to be monitored in real time.

The availability of updated and detailed information at all levels of the mining operation is essential to make informed and timely decisions. The implementation of technology to automate the information system facilitates this process, allowing situations to be consulted in real time and to respond quickly and efficiently to any challenge or change in operating conditions.

Furthermore, given the dynamic and evolving nature of the mining industry, deepening operations requires a mindset of continuous improvement. Based on the findings of this study and the inherent flexibility of the lean methodology, pilot tests can be carried out and experiments with changes in mining activity. This allows you to proactively adapt to emerging challenges, identify opportunities for improvement and further optimize mining cycle performance.

Although this research comprehensively addresses productivity aspects in the mining cycle, it is important to highlight that the application of this tool is not limited only to temporal aspects. It is also useful to evaluate other indicators such as safety or environmental impact. However, these aspects are not the focus of this study, since no modifications will be made regarding them.

Acknowledgment

This work has been possible thanks to the collaboration of the mine works management of the mining preparation of the Esmeralda mine, El Teniente division, Codelco-Chile.

Nomenclature
BP Bypass
CX Cruise
NV-H Sinking level
NV-P Production level
TCT Total cycle time
TP Productive time
TC Contributing time
TNC Non-contributory time
  References

[1] Bocanegra, I.M.H. (2020). El contrato de explotación minera (*) The Mining Contract. https://dialnet.unirioja.es/descarga/articulo/7219666.pdf 

[2] Herrera Herbert, J. (2006). Introducción a los fundamentos de la tecnología minera. Edición Actualizada Y Revisada Para El Curso Académico 2006-2007.

[3] Gómez Botero, P.A. (2010). Lean manufacturing: flexibilidad, agilidad y productividad. Gestión y Sociedad, 3(2): 75-88. https://ciencia.lasalle.edu.co/gs

[4] Soler, V.G. (2011). Lean manufacturing. what is and what is no errors in its most common application and interpretation.https://3ciencias.com/articulos/articulo/lean-manufacturing-que-es-y-que-no-es-errores-en-su-aplicacion-e-interpretacion-mas-usuales/.

[5] Zahraee, S.M., Esrafilian, R., Kardan, R., Shiwakoti, N., Stasinopoulos, P. (2021). Lean construction analysis of concrete pouring process using value stream mapping and Arena based simulation model. Materials Today: Proceedings, 42: 1279-1286. https://doi.org/10.1016/j.matpr.2020.12.955

[6] Tejeda, A.S. (2011). Mejoras de lean manufacturing en los sistemas productivos. Ciencia y Sociedad, vol. 2. http://www.redalyc.org/articulo.oa?id=87019757005

[7] Montoya, C. (2011). El balanced scorecard como herramienta de evaluación en la gestión administrativa. Visión de Futuro, 15(2): 1-25. www.fce.unam.edu.ar/revistacientifica/URLdelDocumento:http://revistacientifica.fce.unam.edu.ar/index.php?option=com_content&view=article&id=251&Itemid=61

[8] Stadnicka, D., Litwin, P. (2019). Value stream mapping and system dynamics integration for manufacturing line modelling and analysis. International Journal of Production Economics, 208: 400-411. https://doi.org/10.1016/j.ijpe.2018.12.011

[9] Seifullina, A., Er, A., Nadeem, S.P., Garza-Reyes, J.A., Kumar, V. (2018). A lean implementation framework for the mining industry. Ifac-Papersonline, 51(11): 1149-1154. https://doi.org/10.1016/j.ifacol.2018.08.435

[10] Baladrón, C., Alarcón, L.F. (2017). Assessing the impact of lean methods in mining development projects. In 25th Annual Conference of the International Group, pp. 137-144. https://doi.org/10.24928/2017/0272

[11] Lööw, J. (2018). Una investigación sobre las prácticas de producción ajustada en la minería. Revista Internacional de Lean Six Sigma, 10(1): 123-142. https://doi.org/10.1108/IJLSS-07-2017-0085

[12] GOBM. Gerencia de Obras Mina lidera proyecto de manejo y compactado de residuos metálicos en El Teniente | CODELCO-Corporación Nacional del Cobre, Chile. Codelco. https://www.codelco.com/operaciones/el-teniente/noticias/gerencia-de-obras-mina-lidera-proyecto-de-manejo-y-compactado-de.

[13] Geovita|SalfaCorp|Ingeniería, Construcción e Inmobiliaria. https://www.salfacorp.com/unidades-de-negocio/ingenieria-y-construccion/empresas-operativas/geovita/.